The safety devices must be checked.
• Move the lift with the load into the end position several times. (see Section 5.1)
•
Check the hydraulic lines again for leak-tightness.
•
Check the anchor fastenings again.
In case of malfunction, firstly inform customer service.
9.3 Commissioning
Before commissioning, a single safety inspection must be done (use the "single
safety inspection" form)
If the lift set up is done by a specialist (factory trained assembler) then he can also do the safety
inspection. If the set up is done by the operating company then a specialist must be tasked with
the safety inspection. The specialist confirms seamless operation of the lift on the set up
protocol for single safety inspection and releases the lift for use.
After commissioning, the set up protocol must be completed and sent to the
manufacturer.
9.4 Changing the assembly location
To change the assembly location the pre-conditions must be met according to the assembly
guidelines. The location change is to be done according to the following sequence.
•
Move the lifting stage upwards to approx. 1,000 mm
•
Remove the tank covers
•
Remove the lifting arm.
•
Lower the lift to the lowest position.
•
Disconnect power.
•
Loosen base plate anchors.
•
Transport the lift to the new assembly location.
•
Assemble the lift according to the procedure during assembly and anchoring before first
commissioning.
Use new anchors. The old anchors are no longer fit for purpose!
Before re-commissioning, a safety inspection must be done by a specialist (use the
regular safety inspection form)
Opera ting Ma nua l a nd Inspection Book
POWER LIFT HL 2.60 SST DG