Warning!! Only lower each column alternately by a max. of 5-10 cm otherwise there is
a danger of falling.
The entire emergency discharge must always be observed by the operator.
The lift must be stopped until the defective parts are exchanged.
The lift may only be operated again once it has been returned to a seamless condition
seen from a safety point of view.
Afterwards do a reset, see sequence Section 6.3 Resetting the lean controller.
Opera ting Ma nua l a nd Inspection Book
Figure 8:
Loosen both red locking nuts on the hydraulic block. Afterwards,
loosen both emergency discharge screws using an Allen key (size
5) by a maximum of 1 rotation anti-clockwise.
Red locking nuts with
emergency discharge crews
Figure 9:
Screw on the long threaded sleeve (available from your
dealer) and tighten clockwise using a suitable tool
(spanner width 24) Lower the lift rails approx. 5-10 cm.
Repeat the process on the next lift rails etc. The lift rails
may only be lowered in steps of 5-10 cm until the entire
lift has reached the lowest position.