Jung JPE 30 NVR Instrucciones De Servicio página 33

Bombas
Tabla de contenido

Publicidad

Idiomas disponibles
  • MX

Idiomas disponibles

  • MEXICANO, página 39
Lifting the load
> Close the draining screws (2) of the jacks in the
clockwise direction (1).
> Connect the compressed air hose to the compressed
air connection (3).
> Connect the jack (1) to connections (7).
> Lift the load by stepping on the foot switch (4).
© JUNG Hebe- und Transporttechnik GmbH
Lowering the load
WARNING
The lowering operation is only performed using the
connected pump. The draining screws of the lifting
devices must remain closed.
> Lower the load by slowly stepping on the foot
switch (5).
Pumps
- 33 -

Publicidad

Tabla de contenido
loading

Este manual también es adecuado para:

Jpe 30/4 nvrJpe 55 nvrJp 26Jpl 15

Tabla de contenido