13 - After positioning the bollard inside the case, remove the lifting eye-
bolts.
Position the blocks on the pipe guide ring. The blocks are necessary in
order to lift the bollard without the treadable flange.
Connect the bollard to the control unit and then lift it electrically. Refer to
instructions supplied with the control unit.
With the bollard completely lifted, adjust its level. Completing this adjust-
ment with the bollard lifted makes it possible to verify, even visually, that
the cylinder is perfectly vertical, a necessary condition for the automation
to operate properly.
See figure alongside.
14 - Verify that the distance between the bollard flange and the upper edge
of the case/flooring is equal to 23-24 mm.
By respecting this distance the treadable flange will be slightly raised com-
pared (1/2mm) to the flooring, limiting the amount of dirt that may infiltrate
the inside of the bollard.
In an effort to reduce possible infiltrations, if the flooring allows it, plan on
a slight slope around the foundation case.
See figures alongside.
15 - With the treadable flange check the final level with respect to the ex-
ternal floor. If required, using the M16 stainless steel dowels, raise the level
and adjust the level positioning. Insert the washers and the M10 hexagonal
head screws. Cover the holes with the rubber caps provided. Carry out
the electrical connection carefully following the diagram supplied with the
control unit. See figures alongside.
ATTENTION - DANGER
NEVER ACTIVATE THE RISING BOLLARD
BEFORE HAVING FIXED THE TREADABLE
FLANGE!
Assembly instructions - VIGILANT 500/I
GB
1/2 mm
23/24 mm
1/2 mm
23/24 mm
VIGILANT - rev.01 - 17