Installation Instructions – OHB Y-Toggle and V-Hanger
Y-Toggle Installation
Fixture to be installed no less than 12" [305mm]
N
ote:
from the ceiling surface.
Fixture CANNOT be used as a surface mounted
fixture.
Cable/Y-Toggle Suspension Installation
1.
Locate and install cable to the support structure with
the cables spaced approximately 21" [534mm] for 2FT
fixture and approximately 43" [1093mm] for 4FT fixture
apart.
2.
Slip the toggle ends through the holes on the upper
flanges of the end plate. (Figure 1.)
Figure 1. Cable/Y-Toggle Installation
3.
Level the fixture by adjusting the cable length to
the support structure while maintaining a minimum
distance of 12" [305mm].
4.
Use the access plate and remove the desired knockout
for supply voltage entry.
5.
Connect input wiring to driver disconnect provided.
6.
Close Cover.
2
COOPER LIGHTING SOLUTIONS
IB507014EN
Installation instructions
V-Hanger Installation
1.
Slide V-Hanger through center hole of last link of chain.
(Figure 2.)
Chain
V-Hanger
Figure 2.
2.
Insert V-Hanger into open mounting slots on fixture and
close hook with pliers to lock into fixture. (Figure 3.)
Figure 3.
3.
Insert S-Hook through center hole of last link of chain
then close with pliers. (Figure 4.)
Chain
Figure 4.
4.
Attach open S-Hook end to appropriate ceiling mounting
eyelet or bracket, then close S-Hook with pliers.
S-Hook