9. Hydraulic oil
a. Fill hydraulic oil until the oil level reaches the mark on the dipstick.
b. For venting of the hydraulic circuit leave the Tank cap for the first 10 lifting movements
opened.
10. Electric connection
Hereby have to be observed the general and local regulation. Therefore, this step can
only be done only by trained/skilled persons/experts.
Pay attention to the necessary supply (see specifications).
11. Control before the first lifting
a. All the screws, nuts etc. are tightened.
b. Check all the hydraulic connections and cylinders for leakage if necessary retighten.
c. Functioning of all push buttons. Take care that when you press the push button down all the
locking catches are unlocked.
d. Correct direction of the motor rotation.
e. Lift and lower the lift 2 to 3 times and check the synchronization of the both carriages.
f. Lower the lift completely and keep pressed the push button „DOWN „approximately 15
seconds so that the hydraulic system will be completely de-aired.
To check the synchronization you could hear if the safety catches are touching the
carriage in the same time.
12. Loading lifting
a. Lift a load on about 1000mm height
b. Lower afterwards the load in the first safety notch (on approx 500mm).
c. The synchronization ropes have to be equally tight.
d. By the next lifting check equalizer synchronization ropes tension, and adjust if necessary.
e. Lower the lift and install the missing
13. After the installation fill out the attached inspection report.
This information is required in a possible case of a potential claim.
2.10 Completion of Work
Before commissioning, check all fastening screws, electrical, pneumatic and hydraulic
lines and, if necessary, tighten these. Warning: in some cases, this must be checked at
regular intervals and tightened if necessary (note in the instructions).
® Copyright ATH-Heinl GmbH & Co. KG, All rights reserved / Misprints and technical changes reserved / As of: 2021-07
covers.
Manufacturer ATH-Heinl GmbH & CO.KG
- 30 -