Optimised sensor installation downstream of the heat
exchanger
The temperature sensor (T0) must be mounted on the flow
downstream of the heat exchanger on the secondary side (wet
sensor) ( Fig. 24 at end of document).
There are two ways to ensure optimised sensor installation
downstream of the heat exchanger ( Item [1] with angled
screw connection and Item [2], Fig. 4 "Optimised sensor
installation"):
24
A
B
1
Fig. 4
Optimised sensor installation
The temperature sensor must be positioned so the
measurement is taken centrally in the pipe.
▶ Use tap extensions to adjust the installation depth of the
low loss header temperature sensor ( Installation
instructions of low loss header sensor set). If installed
correctly, the sensor projects 1-2 cm into the heat
exchanger.
20
24
A
2
T0
0010024454-001
3.4
Electrical connection
▶ Observe electrical regulations and use at least cable
H05 VV-...
3.4.1 Establishing the BUS connection and temperature
sensor (extra-low voltage side)
▶ If the conductor cross-sections vary, use a junction box to
connect the BUS nodes.
▶ Switch BUS nodes [B] via the junction box[A] in star
( Fig. 18 at end of document) or via BUS nodes with 2
BUS connections in series.
B
T0
If the maximum total length of the BUS connections between all
BUS nodes is exceeded or the BUS system has a ring structure,
commissioning of the system is not possible.
Maximum total length of BUS connections:
•
100 m with 0.50 mm
•
300 m with 1.50 mm
▶ To avoid inductive interference: Make sure all low-voltage
cables are routed separately from supply voltage carrying
cables (min. clearance 100 mm).
▶ In the case of external inductive effects (e.g. from PV
systems) use shielded cable (e.g. LiYCY) and ground one
end of the shield. |Connect the shield to the building's
earthing system, e.g. to a free earth conductor terminal or
water pipes, and not to the connecting terminal for earth
leads in the module.
When extending the sensor leads, use the following conductor
cross-sections:
•
0.75 to 1.50 mm
•
1.50 mm
▶ Route cables through the grommets provided and connect
them as shown in the connection diagrams.
2
conductor cross-section
2
conductor cross-section
2
conductor cross-section for up to 20 m
2
conductor cross-section for 20 m to 100 m
MU 100 – 6721804146 (2019/10)