WASTE PETROL DEPLETION
1.
Secure the depletion hose (same as suction hose) to the bulk waste petrol tank and open the
valve.
2.
Close pressure release valve.
3.
Make sure the function switch connect to the air outlet is in close position (see fig 3 below).
4.
Connect main hose in depletion side.
5.
Connect tyre gun to the tank and start pressurising the tank (see fig 4 below).
6.
The waste petrol will be drained into the waste petrol tank immediately.
Function switch in
close position
7.
After operation, close air switch and return main hose to the retaining bracket.
V7019
BGS technic KG
Bandwirkerstr. 3
D-42929 Wermelskirchen
Fig. 4
Tel.: 02196 720480
Fax.: 02196 7204820
mail@bgs-technic.de
Main hose connect
in depletion side
Fig. 3
Connect tyre gun
and pressurise the
tank to deplete
petrol.
www.bgstechnic.com