6. Check before first lifting
a. Check all bolts, nuts, etc. are tight
b. Check all connections and cylinders for leaks and tighten if necessary
c. Check that all buttons works
d. Observe the motor rotation direction
e. Bleed the hydraulic circuit as described in the Maintenance chapter.
For the first lifting operation lubricate the slides of the scissor arms (See lubrication schedule
for grease type)
7. Correctly set limit switch
a. To set the maximum lift, position the lift at a height of 1,900mm
b. Loosen the nuts (1) at the limit switch and set it
c. Tighten the nuts (1) again
d. To set the CE stop, position the lift at a height of 400mm
e. Adjust the lever (2) position at the desired height;
f. Tighten the lever after adjustment.
8. Lifting under load
a. Lift a load to a height of approx. 1,000 mm, check the synchronisation and adjust if necessary
b. While continuing to lift, pay attention to the synchronisation
c. Lower the load and mount the missing covers or ramps
9. After setting up, fill in the attached inspection log.
This information is needed in case of service.