Comprobador digital de la resistencia de tierra
Tabla de contenido

Publicidad

Idiomas disponibles

Idiomas disponibles

(1) Connect the test leads to the meter as follows
Drive deep the Auxiliary Earth Bars P, C in straight line into the ground and ensure that the bars are between 5 and 10 meters apart. Connect
ends of the test leads (black, red and green) , which respectively from the ports E, P, C, separately to the object measured, auxiliary earth
rod P and auxiliary earth C.
Attention: Drive the auxiliary rods where the earth is damp; in case that no other earth but clay, sand or gravel, which are dry, are available,
spray some water onto them to keep them damp; in case the measurement is performed on a concrete floor, place the auxiliary earth rods
horizontally and spray some water onto them or cover them with damp cloth.