PRELIMINARY STEPS: Installing the draft shield and setting up the balance
Installing the pan support and weighing pan is always done in the same manner, regardless of whether a draft shield and/or in-use cover is used or not. With the
PE360, the draft shield provided should be installed, so as to achieve measurement values that are not affected by drafts.
Every PE balance provides reliable measuring values, even under less than favorable ambient conditions.
However, it is preferable to set the balance up at a stable location, with as little draft as possible and that is not in direct sunlight.
Installing the draft shield (PE360)
The base (19) is installed in the factory. If it was
subsequently removed, proceed as follows:
– Remove weighing pan and pan support.
– Place base (19) on the balance and turn it
clockwise until it stops.
– Place pan support and weighing pan on
balance.
Level indicator field installation kit
– Depending on the height of the draft shield
required, place low or high middle section
(20) on the base.
– Place cover (21) with the two snaps on the
middle section.
If wished, a glass draft shield can be ordered for the
PE360, see ACCESSORIES.
Balance location
– Stable base, that is vibration-free and
horizontal.
– No large temperature fluctuations.
– Avoid direct sunlight.
– Find a location free of drafts.
– At the selected location, connect power cable
(14).