6.-DRAINAGE
Drainage should be located below the level of the machine, at 5,9'' (150 mm) minimum.
It is convenient that the drainage pipe is 1,18'' (30 mm) inside diameter and with a minimum gradient of 0,36''/ft (3 cm/ meter), see
figure.
CORRECT
INCORRECT
INCORRECT
7.-ELECTRICAL CONNECTION
IT IS MANDATORY TO GROUND THE EQUIPMENT: To avoid possible discharges on individuals or damages to the equipment,
the machine should be grounded following local and/or national regulations as needed. THE MANUFACTURER SHALL BE HELD
HARMLESS IN CASE OF DAMAGES ARISING DUE TO THE LACK OF THE GROUND INSTALLATION.
In case the supply cable is damaged, it should be replaced by a cable of special assembly to be furnished by the manufacturer or
after-sales service. Such replacement should be performed by qualified technical service only. The machine should be placed in
such a way that allows a minimum space between the back and the wall to allow an easy access and without risks to the cable plug.
Mind the socket. It is convenient to install adequate switches and circuit breakers.
Voltage is indicated in the nameplate. Variation on voltage above the
10% stated on the nameplate could result on damages or
prevent the machine start-up.
In case the ice maker is not fitted with a SUPPLY CORD and a plug, or with other means for disconnection from the supply mains
having a contact separation in all poles that provide full disconnection under overvoltage category III conditions, then means for
disconnection must be incorporated in the fixed wiring in accordance with the wiring rules.
ATTENTION: The appliance requires an independent power supply of proper capacity. See the nameplate for electrical
specifications. Failure to use an independent power supply of proper capacity can result in a tripped breaker, blown fuse, damage to
existing wiring, or component failure. This could lead to heat
8.-INSTALLATION OF MODULAR EQUIPMENTS ON TOP OF BINS
Modular ice makers should be installed on top of bins, following the instructions contained in this manual.
The resistance and stability of the container-machine/s assembly should be verified, as well as the fastening elements. Follow bin