Descargar Imprimir esta página

Key Automation STAR 2024 Instrucciones Y Advertencias Para Su Instalación Y Uso página 6

Motorreductor para cancelas batientes

Publicidad

Idiomas disponibles
  • MX

Idiomas disponibles

  • MEXICANO, página 20
EN
5 - TESTING AND COMMISSIONING THE AUTOMATION
The testing of the system must be performed by qualified techni-
cians who must perform the tests required by relevant legislation
related to risks, ensuring compliance with the provisions of the regu-
5.1 - Testing
All system components must be tested following the procedures out-
lined in the respective instruction manuals.
Check that they meet the guidelines in Chapter 1 - Safety warnings
Check that the gate or door can move freely once the automation
is unlocked, and that they are in equilibrium and stationary if left in
any position.
Check the correct operation of all connected devices (photocells,
5.2 - Commissioning
Following the successful testing of all (and not just some) devices in
the system you can proceed with the commissioning.
You must prepare, and keep for 10 years, the technical file of the
system with the wiring diagram, drawing or photo of the system,
risks analysis and solutions adopted, manufacturer declaration of
conformity of all devices connected, instruction manual of each de-
vice and maintenance schedule of the system.
Fix on the gate or door a plaque indicating the automation data, the
name of the person responsible for the commissioning, the serial
number and year of construction, the CE mark.
6
lations, in particular the EN12445 standard, which specifies the test-
ing methods for the automation of doors and gates.
sensitive edges, emergency buttons, etc.), testing the opening, clos-
ing and stopping of the gate or door via the connected control de-
vices (transmitters, buttons, switches).
Carry out measurements of the impact force, as prescribed by
standard EN12445 adjusting the functions of speed, motor force and
deceleration of the unit if the measurements do not give the desired
results until you find the right setting.
Attach a plaque indicating the steps required to manually unlock the
system.
Implement and deliver to the end user the declaration of conformity,
the instructions and warnings for use for the end user and the main-
tenance schedule of the system.
Make sure the user understands proper automatic, manual and
emergency operation of the automation.
Inform the end user in writing of the dangers and risks still present.

Publicidad

loading

Este manual también es adecuado para:

Star 3024