8. Installation
8.3.
Setting up of the unit
In general, the delivered installation drawing is the basis to fulfill the structural
conditions. Nevertheless, some points must be respected when setting up the unit.
All installation works (sanitary and electric) may exclusively
effect by qualified specialists.
The room must correspond to the connection conditions
indicated in the installation drawing.
The transport of the unit may only effect at the frame.
1.
The tub must stand horizontally on an even, firm subsoil. Small unevenesses
of the floor can be evened by the adjustable tub feet.
2.
If the delivered sanitary connection hoses must be elongated because of
structural reasons, generally use metal cloth reinforced high pressure hoses.
3.
The tub drain needs a DN 50 connection. The canalisation must not be
smaller. Discharge times would be negatively influenced.
4.
To assure a reasonable functionality of the unit, the constructional water flow
pressure should be 3 - 3,5 bar. Filling times are influenced by the flow
pressure.
5.
For the electrical installation generally provide an all-pole, illuminated main
switch near the unit.
A voltage equalising cable is to be provided.
Furthermore, the power line in the sub-distribution must be carried via a
ground fault circuit interrupter with a tripping characteristic of 30 mA and a line
safety switch.
6.
The installation must be followed by a documented safety-related control
according to DIN VDE 0701 T1.
(The drawings correspond to any configuration, they could differ from the original display!)
Manual Aroma 1.5-23
20.04.09
39