Purging Procedures Leak Test; Drain Piping Work - Mitsubishi Electric Mr.SLIM PEAD-M35JA Manual De Instalación

Ocultar thumbs Ver también para Mr.SLIM PEAD-M35JA:
Tabla de contenido

Publicidad

6. Refrigerant piping work

6.4. Purging procedures leak test

PURGING PROCEDURES
Connect the refrigerant pipes (both the liquid and gas pipes) between the indoor
and the outdoor units.
Remove the service port cap of the stop valve on the side of the outdoor unit gas pipe.
(The stop valve will not work in its initial state fresh out of the factory (totally closed
with cap on).)
Connect the gage manifold valve and the vacuum pump to the service port of the
stop valve on the gas pipe side of the outdoor unit.
Run the vacuum pump. (Vacuumize for more than 15 minutes.)
Check the vacuum with the gage manifold valve, then close the gage manifold
valve, and stop the vacuum pump.
Leave it as is for one or two minutes. Make sure the pointer of the gage manifold
valve remains in the same position. Confirm that the pressure gage show -0.101MPa
(-760 mmHg).
Stop valve
*Close
Stop valve
*Open
Hexagonal wrench
Service port
*4 to 5 turns
Remove the gage manifold valve quickly from the service port of the stop valve.
After refrigerant pipes are connected and evacuated, fully open all stop valves on
gas and liquid pipe sides.
Operating without fully opening lowers the performance and causes trouble.
Pipe length :
7 m maximum
No gas charge is needed.
Tighten the cap to the service port to obtain the initial status.
Retighten the cap
Compound pressure
-0.101MPa
gauge (for R32/R410A)
(-760 mmHg)
Pressure gauge
(for R32/R410A)
Gauge manifold valve
(for R32/R410A)
Handle
Handle High
Low
Charge hose
Stop
(for R32/R410A)
valve
Vacuum
(or the vacuum
pump
Window
pump with the
function to
Adapter for
Charge hose
prevent the back
preventing
(for R32/R410A)
flow)
the back flow
Pipe length exceeding 7 m
Charge the prescribed
amount of gas.
Leak test

6.5. Drain piping work

• Ensure that the drain piping is downward (pitch of more than 1/100) to the outdoor
(discharge) side. Do not provide any trap or irregularity on the way.
• Ensure that any cross-wise drain piping is less than 20 m (excluding the difference
of elevation). If the drain piping is long, provide metal braces to prevent it from
waving. Never provide any air vent pipe. Otherwise drain may be ejected.
• Use a hard vinyl chloride pipe VP-25 (with an external diameter of 32 mm) for drain
piping.
• Ensure that collected pipes are 10 cm lower than the unit body's drain port.
• Do not provide any odor trap at the drain discharge port.
• Put the end of the drain piping in a position where no odor is generated.
• Do not put the end of the drain piping in any drain where ionic gases are generated.
[Fig. 6-5-1] (P.5)
Correct piping
Wrong piping
A Insulation (9 mm or more)
B Downward slope (1/100 or more)
C Support metal
K Air bleeder
L Raised
M Odor trap
Grouped piping
D O. D. ø32 PVC TUBE
E Make it as large as possible. About 10 cm.
F Indoor unit
G Make the piping size large for grouped piping.
H Downward slope (1/100 or more)
I O. D. ø38 PVC TUBE for grouped piping. (9 mm or more insulation)
PEAD-M·JA model
J Up to 700 mm
N Drain hose (accessory)
O Horizontal or slightly upgradient
[PEAD-M·JA model]
1. Insert the drain hose (accessory) into the drain port (insertion margin: 25 mm).
(The drain hose must not be bent more than 45° to prevent the hose from
breaking or clogging.)
(Attach the hose with glue, and fix it with the band (small, accessory).)
2. Attach the drain pipe (O.D. ø32 PVC TUBE PV-25, field supply).
(Attach the pipe with glue, and fix it with the band (small, accessory).)
3. Perform insulation work on the drain pipe (O.D. ø32 PVC TUBE PV-25) and on the
socket (including elbow).
4. Check the drainage. (Refer to [Fig. 6-6])
5. Attach the insulating material (accessory), and fix it with the band (large,
accessory) to insulate the drain port.
[Fig. 6-5-2] (P.5) *only on the PEAD-M·JA model
A Indoor unit
B Tie band (accessory)
C Visible part
D Insertion margin
E Drain hose (accessory)
F Drain pipe (O.D. ø32 PVC TUBE, field supply)
G Insulating material (field supply)
H Tie band (accessory)
I To be gap free. The joint section of the insulation material meet must be at the top.
[PEAD-M·JA model]
1. Insert the drain hose (accessory) into the drain port.
(The drain hose must not be bent more than 45° to prevent the hose from
breaking or clogging.)
The connecting part between the indoor unit and the drain hose may be
disconnected at the maintenance. Fix the part with the accessory band, not be
adhered.
2. Attach the drain pipe (O.D. ø32 PVC TUBE, field supply).
(Attach the pipe with glue for the hard vinyl chloride pipe, and fix it with the band
(small, accessory).)
3. Perform insulation work on the drain pipe (O.D. ø32 PVC TUBE) and on the
socket (including elbow).
[Fig. 6-5-3] (P.5) *only on the PEAD-M·JA model
A Indoor unit
B Tie band (accessory)
C Band fixing part
D Insertion margin
E Drain hose (accessory)
F Drain pipe (O.D. ø32 PVC TUBE, field supply)
G Insulating material (field supply)
15

Hide quick links:

Publicidad

Tabla de contenido
loading

Tabla de contenido