Installation/Wall-Mounting
WARNING:
WARNING:
the combined weight of the rack and all equipment that will be installed in the rack. The rack can support an
equipment load up to 150 lb maximum, evenly distributed.
Note: Recommended torque for tightening all M5 screws is 35 inch lbs or 3.9 Newton meters.
Configuration
Step 1 Insert one end of the longer vertical mounting rails into the
corners of the bottom panel frame (both panel frames can
be used as a top or a bottom) opposite the mounting side
and secure them with 2 of the M5 button head cap screws
on each side.
1
Step 3 Attach strengthening straps to frame using provided
M6 x12mm Phillips screws.
Left
3
14-02-241-9332FD.indb 3
Do not attempt to mount the rack to the wall with equipment mounted to the rack.
The wall surface, the wall studs and all user-supplied mounting hardware must be able to support
Right
X4
Step 2 Insert the other end of the longer vertical mounting rails
into the corners of the top panel frame opposite the
mounting side and secure them with 2 of the M5 button
head cap screws on each side.
2
Step 4 Before mounting the rack, find the studs in your wall/
mounting surface and make all measurements and/or
guide marks.
Step 5 Using user-supplied hardware, mount the top and bottom
panel frames to the wall. Both mounting frames can
accommodate 5/16" lag bolts.
5
3
16"
(406.4 mm)
22.79"
(578.86 mm)
3/19/2014 4:58:20 PM