UP AND CONFIGURATION

Pre-operation checks

DANGER
Switch off all relevant power supply before making any
connections.
After the installation of the heater kit, check the following before
switching on the circuit breaker:
Filled with water
Make sure that the heater of the heater kit is completely filled
with water.
Air purge
Make sure the air purge is open (at least 2 turns).
Field wiring
Make sure that the field wiring has been carried out according to
the instructions, according to the wiring diagram and according
to the European and national regulations.
Fuses and protection devices
Check that the fuses or the locally installed protection devices
are of the size and type specified in the chapter "Technical
specifications" on page 10. Make sure that neither a fuse nor a
protection device has been bypassed.
Earth wiring
Make sure that the earth wires have been connected properly
and that the earth terminals are tightened.
Internal wiring
Visually check the inside of the heater kit on loose connections
or damaged electrical components.
Power supply voltage
Check the power supply voltage on the local supply panel. The
voltage must correspond to the voltage on the identification label
of the heater kit.
Shut-off valves
Make sure all necessary shut-off valves are open and water flow
is possible.
Fixation
Check that the heater kit is properly fixed.
Damaged equipment
Check the inside of the heater kit on damaged components or
squeezed pipes.
NOTE
Operating the system with the heater not
completely filled with water will damage the
heater.
Once all checks are fulfilled, the heater kit and indoor unit must be
closed and only then they can be powered up.
RKBUHAA6V3+W1
Heater kit for air to water heat pump system
4PW58904-1

Field settings

To activate the heater kit some field settings on the RKHBRD indoor
unit need to be changed.
For details how to change field settings refer to the chapter "Field
settings" of the indoor unit installation or operation manual.

Detailed description

[6-02] Heater kit
Once installed, you can activate the heater kit by changing field
setting [6-02]=1.
From that moment on, the heat pump system will take the heater kit
into account whilst deciding operation. When the heater is actually
operating, the heater symbol ( is shown on the remote controller.
There is no step 1-2 indication.
[8-02] Emergency operation
During emergency mode, heating is only done by the heater kit, not
by the heat pump.
Activation of emergency mode is done by changing field setting
[8-02]=1.
Activating the emergency mode will stop the heat pump operation.
The pump of the indoor unit will be started, but heating itself is done
by the heater kit. If there are no error conditions in leaving or
returning water thermistors, the heater kit can start to follow
emergency operation.
NOTE
Before activating emergency operation, be sure to
activate the heater kit. The heater will stay in
emergency mode until the field setting is set back to
default [8-02]=0.
Benefit kWh rate power supply mode
NOTE
This concerns the benefit kWh rate power supply
mode of the RKHBRD indoor unit. For more details,
refer to the "Field settings" chapter of the indoor unit
installation manual.
If the benefit kWh rate power supply is used for the indoor unit, the
indoor unit will go into emergency operation automatically when the
power supply is interrupted.
F
INAL CHECK AND TEST RUN

Final check

Before switching on the heater kit, read the following:
When the complete installation and all necessary settings have
been carried out, make sure that the service panel of the heater
is closed.
The service panel of the heater can only be opened by a
licensed electrician.
It is the responsibility of the installer to make sure that the air is
purged out of the heater and system.
In order to purge most of the air out of the system, refer to the
chapter "Final check" of the RKHBRD indoor unit installation manual.