BOX INSTALLATION PROCEDURE
C1
Dig a hole big enough to hold
410mm
the box containing the operator
(C1)
345mm
Insert the tube for water
drainage in the prepared hole
(F1)
Insert the sheath for laying the
power cables (F2).
F 2
165mm
F 1
Note: while positioning the box,
keep in mind the minimum
distance there must be between
the pillar and the centre of
rotation of the gate hinge.
75mm
Cement so that the box cannot
be moved, wait for it to dry and
then assemble the operator and
levers.
Distance between
Pillar - Hinge Centre
Pag. 6