JUNO NEW CONSTRUCTION RECESSED JUNCTION BOX HOUSING
WARNING: For your safety, read and understand instructions completely before starting installation.
Before wiring, turn off electricity at the fuse or circuit breaker box.
NOTE: Juno recessed fixtures are designed to meet the latest NEC requirements and
are listed in full compliance with the relevant UL standard(s). Before attempting
installation of any recessed lighting fixture, check your local electrical building code.
This code sets the wiring standards and installation requirements for your locality and
should be understood before starting work. Use of non-Juno trims voids warranty.
PACKAGING CONTENTS
The junction box housing consists of the following: [1] Plaster Frame and Junction Box housing
assembly with bar hangers, [2] trim ring, [3] retrofit mounting bracket, [4] #8 Phillips flat head
screw (x2), and installation instructions. Check for all content prior to installation (Fig 1).
SAVE THESE INSTRUCTIONS
TYPE IC FOR FINISHED
INSULATED CEILINGS
Figure 2
Juno Type IC fixtures are designed for direct
contact with insulating materials which are
approved for this application (Fig. 2). Fixtures
may also be used in non-insulated ceilings.
IMPORTANT: Square ceiling cutout
cannot exceed 4-1/4" x 4-1/4".
INSTALLATION INTO
JOIST CONSTRUCTION
Figure 3
Step 1. Extend bar hangers to fit between
joists. Bar hanger foot is coutoured to easily
align with bottom of joist (Fig 3). Position
fixture by hammering Real-Nails into joists
(Fig 4)
(Note: Bar hanger may be shortened to fit 12"
framing or smaller by breaking at score lines.)
Step 2. Slide fixture along bar hangers into
desired location. Use locking screws or slot
to secure (Fig 5)
Relocating Fixture – Nail can be removed
with hammer claw to allow easy repositioning
of fixture without damaging bar hanger or nail
(Fig. 6).
Step 3. Follow steps 1-4 under Electrical
Connection.
Step 4. When installing in drywall, cut a
square hole measuring 4-1/4" x 4-1/4"
maximum. Do not exceed these hole
requirements.
Note: If installing in fire rated ceiling
assemblies, International Building Code
Secion 714 must be followed.
Figure 4
1300 S. Wolf Road • Des Plaines, IL 60018 • 800-323-5068 • www.acuitybrands.com
©2017 Acuity Brands Lighting, Inc.
INSTALLATION INSTRUCTIONS
Figure 6
Figure 5
Rev 04/19
P4716
IC1JBPF Series
Figure 1
INSTALLATION INTO
SUSPENDED CEILING
Figure 7
Step 1. Locate center of proposed opening
on ceiling tile and cut a square hole
measuring 4-1/4" x 4-1/4" maximum. Do not
exceed these hole requirements.
Step 2. Place ceiling tile in T-bar grid.
Step 3. Place fixture into position and snap
bar hanger foot with integral T-bar notch onto
T-bars (Fig. 7). Additional holes are provided
for securing with wire or screws if desired
(Fig. 8).
Step 4. Follow Steps 1-4 under Electrical
Connection.
Figure 8
1 of 2