Assemble the Gate
Step
4
Gather (Quantity):
(2) Gate Frame Rails
(2) 65 inch (1.65 m) Tension Rods
(8) Clips
Chain Link Fabric
1. Insert swedged end into plain tube for both gate frame rails (4A).
2. Slip both tension rods down through the fi rst diamonds of the fabric on each side (4B).
3. On one side using 4 clips, connect the fabric to the gate frame by clipping the tension rod to the
frame (4C).
4. On opposite side using 4 clips, connect fabric to frame by placing clip on tension rod fi rst and then
clip onto frame by applying downward pressure (4E).
5. Attach 2 tie wires to the bottom of the gate spaced evenly apart (4F). Attach 1 tie wire centred at
the top (4D).
Swedged
End
6
• Steel tubes may have sharp edges. Use care during fabric installation and installing
clips as wire ends may be sharp.
• It is recommended that work gloves be worn.
4A
U.S. Customer Care Center 1-888-632-4453
4B
4C
4D
4E
4F