3. Installation
All measures are expressed in milimeters unless otherwise indicated.
3.1. Preliminary controls
1.
Control the stability and solidity of the zone where the columns are going to be fixed.
2.
Use an omnipolar interrupter with contact distance of at least 3mm.
3.
The connection to the power supply must be seperated than the connections to the security and commanding de-
vices.
3.2. Installation of the column ( Fig. 1, Fig. 3, Fig. 4)
1.
Screw in for 1,5 – 2,0 cm the 4 screws M10x70 in dotation to the base.
2.
Place than the base on the previously prepared base of cement (Fig.3)
3.
The upper part of the base should be clean and perfectly horizontal.
4.
Pass the plastic tubes of the cables through the central opening on the base and check again the stability of the
base.
5.
Unscrewing the 8 screws [10] take off the frontal [8] and the rear cover [9] of the column (Fig. 4 )
6.
Place now the column structure on the base.
7.
Fix now the column to the base with the 4 washers [5] and 4 nuts [4].
8.
Fix the frontal covers [8] of both columns with 4 screws [10].
9.
Now you can fix the chain to the apposite holes on both columns respecting the level X in the middle of the chain
barrier indicated at the table on page 1 (Fig. 5 )
3.3. Electrical connections
Please refer to the instructions of the control unit ACTION for the chain barrier (code: 61622349).
4. Maintanence plan (every 6 months)
1.
Cut the power supply off or disconnect the batteries if present. Clean and grease the guide and the pignons
internally.
2.
See if there are weared parts and replace these if neccessary
3.
Grease the internal transmitting chain.
4.
Check the fixation nuts
5.
Control the electrical connections
6.
Supply the power again
7.
Check out the correct functioning of the obstacle recognition ( encoder system )
8.
Check out the correct functioning of all and of the security commands