Einbauanleitung
Mounting instruction
Instructions de montage
Instrucciones de instalación
Use:
- Floor-height Resopal shower systems are delivered
made-to-measure and do not need to be shortened.
- The kind of utilization of the shower space (splash
protection, movement area, etc.) is to be considered.
- For the installation of the shower system a level, clean,
solid surface free of vibrations and suited for fastening
with Flex tile adhesive must be available.
- The correct fitting of the discharge element is to be
checked.
- The shower system is in general wheelchair-accessi-
ble.
- Suitable only for use indoor.
- Ascending connections must be made at a minimum
distance of 3 mm between floor and Resopal Spa
Styling wall cladding. A minimum distance of 4 mm
must be maintained between the floor-level Resopal
Spa Styling shower system and the adjacent floor. The-
se connections must be sealed durably with silicone!
These connections are maintenance joints!
Please observe the manufacturer's instructions.
The relevant processing guidelines for all trades
working on the job and for the accessories to be
fitted need be observed.
During fitting, protect the surface from damage
using a suitable material such as cardboard.
During installation, care must be taken to ensure a
1
suitable substructure, which must be provided by
the contractor.
The following are permissible:
- mortar-coated hard foam boards
- EPS substructures with at least 25g/l
- screed base
The height of the substructure must be selected
based on the discrepancy in height between the
unfinished floor and the finished floor (see instal-
lation examples as well).
RESOPAL SpaStyling
Example for installation with substructure element (X):
Mounting height/finished floor level
RESOPAL SpaStyling
2 layers of tile adhesive
Substructure element (X)
Edge insulation strips are to be provided locally.
2
Apply Flex tile adhesive to both sides. The chan-
3
nels on the underside of the Loft should be left
clear.
The drain fitting must possibly be lined with sui-
4
table sound absorbing material.
After the installation of the drain fitting, a leakage
5
test must be carried out.
Install the RESOPAL SpaStyling® Shower Element
6
aligned evenly in a balanced position and weigh
it down in the areas shown in picture 11.
Then the slope lines to the drain must be checked.
The processing instructions of the sealing system
7
are to be observed.
Fold the corners of the sealing tape at the pre-
8
marked points. The sealing tape and the resulting
overlaps must be completely sealed with sealing
compound.
Insert the sealing tape into the applied sealing
9
compound.
Cover sealing tape with KMK sealing compound.
10
Follow the installation instructions for the drain
11
body. The installation key must be kept for main-
tenance purposes.
Shower Elements
®
Punktablauf
Point drainage
Écoulement à points
Desagüe central
Shower Elements
®
120 mm
- 50 mm
-10 mm
= 60 mm
6 / 9