On-Site Installation; Supply Line; Fuse Protection Rating; Opening The Device - Mennekes eMobility-Gateway Manual De Instrucciones

Tabla de contenido

Publicidad

Idiomas disponibles
  • MX

Idiomas disponibles

  • MEXICANO, página 115
Permitted environmental conditions
Ambient temperature
Average temperature over
24 hours
Altitude
Relative humidity

5.3 On-site installation

T
T
DANGER
Fire hazard due to device overload.
There is a fire hazard due to overloading of the device
caused by unsuitable circuit breaker and supply line.
f Lay out the supply line and the circuit breaker accord-
ing to the technical data of the device.
The connection must be accomplished accord-
ing to protection class II, compliant with DIN EN
60950.
f When installing, please note the applicable
requirements for compliance with protection
class II including functional earth.

5.3.1 Supply line

f Lay out the supply line according to the technical data
of the device.
Î "4. Technical data"
When dimensioning the supply line (cross sec-
tion and cable type), always ensure the following
local conditions:
„ Type of installation
„ Cable parameters per unit length
„ Line length
f Route supply line and possibly data and control lines to
the appropriate locations.
8
-25 ... +40 °C
< 35 °C
max. 2000 metres above
sea level
max. 95 %
(non-condensing)

5.3.2 Fuse protection rating

f Observe valid national regulations.
f Lay out the circuit breaker according to the technical
data of the device.
Î "4. Technical data"

5.4 Opening the device

Fig.: 5. Opening the device
f Disconnect the device from the mains.
f Open the lock on the front by using the supplied key.
f Open the cover by pressing.
f Swing the enclosure cover downwards.

Publicidad

Tabla de contenido
loading

Tabla de contenido