Refrigerant piping

 Refrigerant piping
1. Use copper pipe with 0.8 mm or more thickness.
2. Flare nut and flare works are also different from
those of the conventional refrigerant.
Take out the flare nut attached to the main unit of the
air conditioner, and use it.
REQUIREMENT
When the refrigerant pipe is long, provide support
brackets at intervals of 2.5 - 3 m to clamp the refrigerant
pipe. Otherwise, abnormal sound may be generated.
CAUTION
CAUTION
IMPORTANT 4 POINTS FOR PIPING WORK
1. Remove dust and moisture from the inside of the
connecting pipes.
2. Tight connection (between pipes and unit)
3. Evacuate the air in the connecting pipes by using
VACUUM PUMP.
4. Check the gas leakage. (Connected points)
 Pipe size
AP005, AP007
Model
AP015, AP018
MMU-
AP009, AP012
name
type
Gas side
9.5 mm
Pipe size
Liquid side
6.4 mm
105-EN
 Permissible piping length and
height difference
They vary according to the outdoor unit.
For details, refer to the Installation Manual attached to
the outdoor unit.
Flaring
• Cut the pipe with a pipe cutter.
Remove burrs completely.
Remaining burrs may cause gas leakage.
• Insert a flare nut into the pipe, and flare the pipe.
As the flaring sizes of R410A differ from those of
refrigerant R22, the flare tools newly manufactured
for R410A are recommended.
However, the conventional
tools can be used by adjusting
projection margin of the
copper pipe.
▼ Projection margin in
flaring: B (Unit: mm)
Rigid (Clutch type)
R410A tool
used
Outer dia. of copper pipe
R410A
6.4, 9.5
type
0 - 0.5
12.7
12.7 mm
▼ Flaring dia. meter size: A (Unit: mm)
6.4 mm
Outer dia. of copper pipe
6.4
9.5
12.7
* In case of flaring for R410A with the
conventional flare tool, pull it out approx.
0.5 mm more than that for R22 to adjust
to the specified flare size.
The copper pipe gauge is useful for
adjusting projection margin size.
– 53 –
Tightening connection
CAUTION
CAUTION
Do not apply excessive torque. Otherwise, the nut may
crack depending on the conditions.
Outer dia. of copper pipe
6.4 mm
9.5 mm
12.7 mm
▼ Tightening torque of flare pipe connections
Pressure of R410A is higher than that of R22.
(Approx. 1.6 times) Use a torque wrench, tighten the
flare pipe connecting sections which connect the
indoor and outdoor units of the specified tightening
torque.
B
Incorrect connections may cause not only a gas leak,
but also a trouble of the refrigeration cycle.
Align the centres of the connecting pipes and tighten
the flare nut as far as possible with your fingers. Then
tighten the nut with a spanner and torque wrench as
shown in the figure.
Conventional
tool used
R410A
1.0 - 1.5
Work using double spanner
REQUIREMENT
A
+0
–0.4
Tightening with an excessive torque may crack the nut
R410A
depending on installation conditions.
9.1
Tighten the nut within the specified tightening torque.
13.2
16.6
Piping with outdoor unit
A
Shape of valve differs according to the outdoor unit.
For details of installation, refer to the Installation
Manual of the outdoor unit.
 Leak check test, evacuation
and other procedure
For leak check test, evacuation, addition of refrigerant,
and gas leak check, refer to the Installation Manual
attached to the outdoor unit.
REQUIREMENT
Unit: N•m
Do not supply power to the indoor unit until the leak
Tightening torque
check test and evacuation are completed. (If the indoor
14 - 18 (1.4 to 1.8 kgf•m)
unit is powered on, the pulse motor valve is fully closed,
which extends the time for vacuuming.)
34 - 42 (3.4 to 4.2 kgf•m)
49 - 61 (4.9 to 6.1 kgf•m)
Open the valve fully
Open the valve of the outdoor unit fully.
For details, refer to the Installation Manual attached to
the outdoor unit.
Heat insulation process
Apply heat insulation for the pipes separately at liquid
side and gas side.
For the heat insulation to the pipes at gas side, use the
material with heat-resisting temperature 120 °C or
higher.
Apply the attached heat insulation to the pipe
connecting section of the indoor unit securely without
gap.
REQUIREMENT
• Apply the heat insulation to the pipe connecting
section of the indoor unit securely up to the root
without exposure of the pipe. (The pipe exposed to the
outside may causes water leak.)
• Wrap heat insulator with its slits facing up (ceiling
side).
Wrap the pipe with the attached heat insulator
without any gap between the indoor unit.
The seam must be faced upward
Indoor unit
(ceiling side).
Heat insulation
Union
pipe
(Accessory)
Flare nut
Heat insulator
of the pipe
Banding band
(locally
procured)
106-EN