6. INSTALLATION.
6.1. LOCATION.
The batteries in the
an enclosure with IP54 degree of protection, suitable for indoor and
outdoor installations. The following factors should be taken into
account when selecting an installation location for the inverter and
battery:
The wall on which the batteries are mounted must be able to
1.
support their weight.
The batteries must be installed in a well-ventilated environ-
2.
ment.
Make sure that the batteries are not exposed directly to
3.
strong sunlight to avoid operation at excessive temperatures.
The batteries should be installed in a place sheltered from
direct sunlight and rain.
Install the batteries at eye level for ease of maintenance.
4.
The ambient temperature of the place where the batteries are
5.
installed must be between 0ºC and +50ºC.
Do not touch the batteries during operation and install them
6.
out of the reach of children.
6.1.1. Installation location.
We recommend installing the batteries of hybrid inverters
indoors. However, if there is no choice but to install out-
doors, Fig. 7 shows recommended locations, as well as those to
avoid:
Fig. 7. Recommended locations for the inverter and batteries.
Do not store flammable and/or explosive materials near
the inverter and batteries.
Warning
30
EQX2-Batt
series have been designed with
6.2. ASSEMBLY PROCESS.
6.2.1. Installing the base.
Check the installation area and the floor level.
1.
Place the base on the ground, ensuring that it is level and
2.
stable.
Measure with a spirit level
Fig. 8. Adjusting and levelling the base.
The distance between the base and the wall should be
3.
between 20 mm and 120 mm.
Fig. 9. Distance to the wall.
6.2.2. Installing the module.
After installing the base, remove the protective film from the
1.
terminals and reposition the remaining battery module and the
control module.
Fig. 10. Removing the protective film.
SALICRU