50/136
Siemens
Building Technologies
6.4 Commissioning and optimizing the
capacity controller
The controller is commissioned as described in chapter 5.
If possible, it should be commissioned using only pure superheat
control.
After optimizing the control parameters as described in section
5.5, capacity control must be configured and parameterized. In
principle, the parameters (XP, TN) of the capacity controller are to
be optimized according to section 5.5. They must always be
selected such that they are considerably greater than the
parameters of the superheat controller.
CPS40
CE1U3372XX / H 74 319 0555 0 d
2013-10-01