Energi Savr Node
Step 3: Load wiring
The Energi Savr Node unit operates at 120-277 V . Use the following instructions to wire line voltage loads to the Energi Savr Node
unit.
WARNING! Danger of Shock. May result in serious injury or death. DO NOT WIRE WHEN LIVE! Switch off power to all power
feeds via circuit breaker before wiring or servicing the Energi Savr Node unit.
The Energi Savr Node unit is a feed-through device. This means that each switched output needs the Line and Load wires. THERE IS
NO INTERNAL CONNECTION BETWEEN THE CONTROL POWER TO THE UNIT AND THE SWITCHED OUTPUTS.
Feed-Through Wiring Example 1: 4 Circuits, Multiple Feeds
Hot
Hot
Hot
Hot
Neutral
Neutral
Neutral
Neutral
Neutral
Distribution
Ground
Panel
Neutral Wires
Hot
Neutral
0-10 V Wiring (QSN-4T16-S only)
• 20 AWG to 12 AWG (0.5 mm
• Strip length: 1/4 in (6 mm)
• Torque: 5 in-lb (0.5 N
• Connect only NEC
only non-NEC Class 2/PELV circuits to 0-10 V zones
1-4.
Lutron
4
|
®
0-10 V / Softswitch
TM
Ground Bar
Zone Switching:
120-277 V
0-10 V Zones:
(QSN-4T16-S only)
to 4.0 mm
2
m)
•
Class 2/PELV circuits or connect
®
|
Installation Guide
®
• Two (2) 14 AWG to
• Strip length: 3/8 in
• Torque: 7 in-lb
• 0-10 V zones 1-4 are not isolated from each other.
)
• Negative (–) terminals are not internally connected
2
to each other—both positive (+) and negative (–)
connections must be made.
• Follow all national and local codes for separation
requirements.
Energi Savr Node
TM
LOAD
LOAD
LOAD
LOAD
Load Wiring:
12 AWG (2.5 mm
to
2
4.0 mm
)
2
(8.5 mm)
(0.79 N
m)
•
0-10 V Wiring
(QSN-4T16-S only)
0-10V / Softswitch
Installation Guide
®