4. Parts
See Annex T1 for an overview of the parts and their mass.
5. Assembly instructions
See Annex T2 for an overview of the assembly instructions.
6. Check before use
1. Check that the rolling tower is horizontal (check using a spirit level).
2. Check that the rolling tower is assembled in accordance with this manual and in conformity with the configuration and ballast table.
3. Check that the environmental factors, such as swinging doors, awnings that operate automatically, aboveground electrical cables, traffic
and/or passers-by, etc., do not lead to dangerous situations.
4. Check that the rolling tower can be used safely and that it is suitable for the intended purpose.
7. Assembling the RS TOWER 51, 51+ and 52
Mount the parts according to the steps shown in Annexes T3 and T4. Attach all connections as shown in Annex T2. See the table below for
the references to the annexes that include the configuration table and the composition per type of rolling tower.
Configuration
RS TOWER 51 / 51+
RS TOWER 52
A. Base section
Determine the working height you want to reach. See also annex T3 composition A (single width); annex T4 composition A (double width).
A1: Working height of an even number of metres
1. Start with a 4-rung frames (part B)
2. Put the wheels into the frames, put the brakes on and put them in an
outward direction [T2 fig. F1 - F3].
3. Place horizontal braces (part G) under the first rung on the vertical
[T2: fig. F4 - F5].
4. Place the 7-rung frames (part A) and lock them [T2: fig. F6 - F8].
5. Place the Safe-Quick® Guardrail(s) (part F) on the sixth rung with the
instruction label facing the inside [T2 fig F14 - F18].
6. Adjust the base section using a spirit level.
7. Assemble the triangle stabilisers (part I) [T2 fig. F9 - F13].
B. Middle section
See also T3 composition B (single width); T4 composition B (double width).
B1: Working height of an even number of metres
1. Place the Safe-Quick® Guardrail(s) (part F) on the top rung with the
instruction label facing the inside [T2 fig F14 - F18].
2. Place the platform with trapdoor (part D) [T2: fig. F19 - F22]
3. Access the platform by going through the trapdoor.
4. Repeat the steps until you reach the required platform / working height.
C. End section
See also T3 composition C (single width); T4 composition C (double width).
1.
Place the toe board set (part J)
This manual described the composition that starts with installing the Safe-Quick Guardrails®. In addition to this composition, it is also possi-
ble to start with diagonal braces (part H). For this purpose, replace the Safe-Quick Guardrails® of RS TOWER 51 with two diagonal braces for
RS TOWER 51 and with four diagonal braces for RS TOWER 52. See Annex T10 for these options.
Annex
T5
T6
A2: Working height of an odd number of metres
1. Start with a 7-rung frame (part A)
2. Put the wheels into the frames, put the brakes on and put them in an
outward direction [T2 fig. F1 - F3].
3. Place horizontal braces (part G) under the first rung on the vertical
[T2: fig. F4 - F5].
4. Place the Safe-Quick® Guardrail(s) (part F) on the top rung with the
instruction label facing the inside [T2 fig F14 - F18].
5. Place the platform (part D) on the third rung of the 7-rung frames
(T2 fig. F20 - F22].
6. Adjust the base section using a spirit level.
7. Assemble the triangle stabilisers (part I) [T2 fig. F9 - F13].
B2: Working height of an odd number of metres
1. Access the temporary platform (part E).
2. Place the 7-rung frames (part A) and lock them [T2 fig. F6 - F8].
3. Place the Safe-Quick® Guardrail(s) (part F) on the top rung with the
instruction label facing the inside [T2 fig F14 - F18].
4. Place the platform with trapdoor (part D) [T2: fig. F19 - F22]
5. Access the platform by going through the trapdoor.
6. Repeat the steps until you reach the required platform / working height.
7
www.altrex.com
EN