5. Assembly/installation

5.5 Completing work

1. Slowly open the shut-off valves in the flow and return.
2. Check the coupling fittings, meter and temperature sensor for leaks.
3. Press the button on the meter to switch on the display.
• To check the meter, the actual values for energy consumption, temperatures and flow can be viewed on the
display (see "7. Display options" at page 52).
• If a fault message is displayed (see "8. Fault" at page 57), it must be cleared.
4. Fit a lead seal to the measuring capsule with housing or the coupling housing and temperature sensors.
5. Fill out the transfer log and hand over to the end user.