Operating procedure at the fi rst start up
GB
•Undertake the electric wiring for the plant and
check when the card is switched off.
display
•Unblock the gate and check its movement (the
rack must not be supported by the motor pinion).
The stroke of the gate must not have any areas of
stiffness during movement, it must be smooth.
E
LED indicator for
power supply
•Block the gate and supply current to the station.
At this point the electric mains detection led will
r|-00
r-|00
-
light up and the display will show
or
where the horizontal line (
)
indicates the opening direction of the gate. If this does not occur check that the
station receives power and check the inputs activated (see the description of the
display diagnostics).
•Activate the safety devices one at a time and check that the display shows the re-
lative diagnostics wording. For example, activate the photoelectric cell and check
pho
that the message
shows on the display.
apprendimento
Enter the menu and select the item
(learning).
Operating with encoders: the fi rst two manoeuvres help to identify the start and
end of the stroke of the motor. The two that follow detect the speed of the motor
when the gate is closing and opening. In this phase, monitor the values shown
on the display.
Operating without encoders: the motor undertakes two manoeuvres during which
the time required to complete a stroke, is calculated.
ok
•At the end of the learning phase the display will show
if programming was
err
done correctly, or
if errors occurred. To exit the programme press the select
key.
•Correctly set the levels of anti-crushing force in opening and in closing, these
must be greater than the maximum values viewed during learning.
WARNING: this regulation can infl uence the degree of safety of an automated
device.
•Carry out some test cycles checking the correct operation of the entire system.
•Measure the force of impact of the gate according to the specifi cations of regu-
lation EN12445.
21