Head And Boom Operation - Greenlee G1 Versi-Tugger Operación Manual

Tabla de contenido

Publicidad

Idiomas disponibles

Idiomas disponibles

Head and Boom Operation

The G1 Versi-Tugger is equipped with a multi-position
head and boom system. The puller head has 5 positions
and the boom has 4 positions.
To adjust the position or orientation of the boom or
puller head:
• Remove the respective quick release pin
• Reorient the component to its desired position
• Reinsert the quick release pin.
No matter the situation, always ensure that the conduit
engagement notch properly interfaces with the conduit
or conduit nut. In addition, always orient the head so
the rope or pulling line is not rubbing on the edge of the
conduit, or on stationary components of the puller.
Although each pulling situation has unique setup
requirements, typical up-pull, down-pull, and side-pull
positions are shown below:
1. Head-Adjustment Pin and Conduit
Engagement Notch
Orientation Locking Holes
2. Boom Adjustment Pin
Orientation
Locking
Hole
Note: The lines on the boom indicate the engagement point of each length when lined up with the top of the
mount. You may need to rotate the boom to engage.
Greenlee Tools, Inc.
Conduit
Engagement
Notch
Quick-Release Pin
Boom
Boom
Adapter
Quick-Release Pin
3. Up-Pull Head Orientation
4. Down-Pull Head Orientation
Rope or
Pulling Line
5. Side-Pull Orientation
Rope or
Pulling Line
13
4455 Boeing Dr. • Rockford, IL 61109-2988 USA • 815-397-7070
G1 Versi-Tugger™
Rope or
Pulling Line

Publicidad

Tabla de contenido
loading

Tabla de contenido