Fitting procedure
1. Checking the strength of the
installation location
The ceiling-hanging bracket weighs approximately 16 kg
(35.3 lbs).
Refer to the instruction manual of the plasma display,
and check the weight of the plasma display unit which
will be fitted into the ceiling-hanging bracket.
Refer to the outline drawing of the ceiling-hanging
bracket shown on the right, and check the ceiling
strength at the eight installation positions shown. If the
strength at any of these positions is lacking, provide
sufficient reinforcement.
2. Prepare the ceiling unit
Remove the protective sheets (8 sheets) for the bracket
of the ceiling unit at four locations.
Set a spring washer
and fix at the position show on the right.
(Tightening torque: 1.5 to 1.8 N•m)
Remove the two M8 assembly bolts from the ceiling unit
and separate the upper and lower sections of the unit.
• Use the removed M8 assembly bolts when attaching the
ceiling unit (lower section).
3. Install the ceiling unit (upper section)
Before installing the upper section on the ceiling, pass
the wiring through the pipe as shown in the figure on the
right. Use an earthed extension cord for the power cord
(not supplied).
Pass the other device connection cables through the
same way.
Make holes for inserting M12 bolts on the ceiling using
a method appropriate for the ceiling structure. Install
the upper section using a hex socket bolt (M12) (not
supplied), flat washer and spring washer.
* Attach a ceiling cover
using three truss tapping screws
14
on the rotation stop screw
to the ceiling board if needed
.
Ceiling installation holes (8)
14
(0.6)
Ceiling unit
(upper section)
,
M8 assembly bolt
Ceiling unit
(lower section)
Unit: mm (inches)
350 (13.8)
300 (11.9)
200 (7.9)
Front
(Back side
connection part)
Rotation stop
screw
Spring washer
Flat washer
Spring washer
M12 bolt
Device connection cables
Earthed power extension cord
Ceiling cover
Truss tapping screw