Installation to I-beam
• Installer must verify that the supporting beam will safely support the combined weight of all attached equipment and
hardware.
Thread two bolts (M) through four washers (N),
1
ceiling clamp (L), ceiling assembly (C), and two
locknuts (O) as shown.
Repeat for second ceiling clamp.
L
C
Lift ceiling assembly (C) up to I-beam and slide
3
ceiling clamps (L) as close to the center of the
I-beam as possible. NOTE: Tube of ceiling
assembly should be centered below I-beam.
Alternate between tightening bolts (M) of right
clamp and left clamp until bolts evenly apply force
to each clamp.
I-BEAM
M
LEFT CLAMP (L)
WARNING
M
N
M
N
O
M
RIGHT CLAMP (L)
C
TUBE
4 of 24
Thread four hex nuts (P) onto four bolts (M).
2
Thread four bolts (M) into side of ceiling assembly
(C), but do not tighten.
C
P
Tighten bolts (M) on sides of ceiling plate
4
assembly just until they touch the ceiling clamp.
Tighten hex nuts (P) until they touch the sides of
ceiling plate assembly.
P
M
ISSUED: 08-09-10 SHEET #: 061-9059-5 07-08-15