6.1 MAINTENANCE PLAN - Summary table
INTERVAL
WHEN THE MACHINE lS NEW
AT THE BIGINNING OF
THE SEEDING SEASON
EVERY 8 WORKING HOURS
EVERY 50 WORKING HOURS
EVERY SIX MONTHS
EVERY PERIODICALLY
EVERY FIVE YEARS
REST PERIODS
It is in the interests of the user to follow these instructions carefully, as when work recommences, he will fi nd the equipment in perfect
condition.
cod. G19501383
USE AND MAINTENANCE
- Grease all parts indicated by transfer nr. 14 ('GRASE') at page 47 of this leafl et.
- Lubricate all the transmission chains with mineral oil (SAE 80W-90).
- After the fi rst hours of work check that all the bolts are still tight.
WARNING! Do not over-tighten the screws holding the case (C, Fig. 56). It should be able
to oscillate.
- Check the pressure of the tyres (see technical data table).
- Lubricate all the transmission chains with mineral oil (SAE 80W-90).
- Check the fi xing and the state of wear of all the suction tubes and the delivery tubes for
fertilizer and other chemical products.
- Run the seeding machine loadless, the airfl ow clears the pipes of condensation and removes
any impurities.
- Check the tensioning of the aspirator belt (Fig. 21).
- Lubricate all the transmission chains with mineral oil (SAE 80W-90).
- Grease the universal joint spiders.
- Grease the bevel gear pair of the cardan shaft of the planting units (1, Fig. 56).
- Inspect the condition of the seed plates; if any of the pegs are missing or bent, replace the
plate with an original spare; if there are circular scratches on the plates they must not exceed
1/3 of the disc thickness.
- Clean the seed distributor carefully and thoroughly; replace the cover seal if necessary.
- Check the tensioning of the aspirator belt (Fig. 21).
- Make sure the toothed wheels are properly aligned and the transmission chains are tensioned
to prevent them from wearing out in little time or a failure affecting the transmission parts.
- Check that all the bolts are still tight.
- Grease all the joints of the row marker.
- Oil the height adjust bolt (2, Fig. 56).
- Grease the drive wheel oscillating bearings (3, Fig. 56).
- Check the pressure of the seed drill tyres (see «3.1 Technical Data»).
- To replace all the tubes of the hydraulic systems.
At the end of the season, or if a long period of rest is foreseen it is advisable to:
1) Wash the equipment thoroughly with water, especially the chemical substance hoppers,
then dry them. Clean the electrical components only with a dry cloth.
2) Carefully check for worn or damaged parts and replace then where required.
3) Check the state of wear of the transmission chains and toothed wheels. Replace damaged
or worn out parts, if required. Use solvent to clean the transmission chains, the toothed
wheels and the chain stretchers. Lubricate with mineral oil (SAE 80W-90) when dry.
4) Adjust the belt of the diffusion air pump and and replace it if necessary.
5) Firmly tighten all screws and bolts.
6) Apply protecting oil to all unpainted parts.
7) Protect the equipment with a (nylon) cover.
8) Then position it stably in a dry place out of the reach of unauthorized people.