Assembly
2.4.1 Assembly steps
•
excavation
•
assemble the supporting braces
•
pour the concrete slab
•
assemble the wooden structure
•
install the filtration system and pool fittings
•
assemble the vertical section of the ladder
•
lay the waterproofing membrane
•
install the coping and finishing trim
•
wiring
2.4.2 Tools
Excluding the materials required for excavation and pouring the concrete slab, we recommend that you
have the following equipment on hand:
•
measuring tools: decameter, rope, big spirit level
•
mallet
•
drills and drill bits, flat head screw diver, cross head screw driver, drill bit diameter 10 mm
•
cutting tools: Stanley knife, metal saw, hole saw diameter 60 mm
•
tube or socket wrench (13 and 17mm), set of Allen keys
•
finishing tools: sand paper, lime fine
•
tools for glueing pipework: medium sand paper, PVC stripper
2.4.3 Assembly time
Excavation and earthworks: 1 TO 2 DAYS DEPENDING ON THE MATERIALS USED
Metallic structure: ½ DAY (WITH 2 PEOPLE)
Pouring the slab: ½ DAY (WITH TWO PEOPLE) DEPENDING ON THE MATERIALS USED
Wooden structure: 1 TO 2 DAYS (WITH TWO PEOPLE - THE TIME INDICATED DOES NOT
INCLUDE THE CONCRETE CURING TIME)
Curing of the concrete slab: 21 DAYS (3 WEEKS)
CAUTION
Once the structure has been assembled, the liner must be fitted and the pool must be filled with water
within at most 5 days. Past this time limit, the structure will need to be carefully inspected to ensure
the absence of any deformations (movement of the slats, shrinkage, etc.) that could impact the
structural integrity of the work. In the event that gaps appear between the slats, refit them perfectly
before fitting the liner.