Application areas
Tamper-proof valve for connection,
maintenance and inspection of diaphragm
expansion vessels in expansion lines of heating
systems and solar systems with a maximum
concentration of 50 % glycol in the water.
Application
 Suitable for the installation in closed heating
systems as per DIN EN 12828.
"Shut-off devices must be sufficiently
secured against inadvertent closing (e.g.
tamper-proof valve with wire and lead seal)."
 For shutting off expansion tanks from
heating systems for maintenance work
under consideration of DIN EN 13831.
"Expansion tanks with diaphragms must be
arranged in such a way that the maximum
permanent temperature of 70 °C required by
DIN EN 13831 cannot be exceeded or can
only be exceeded for a short period of time."
Specifications
Operating temperature range:
Operating pressure:
Emptying rate:
Mounting information
 The tamper-proof valve (3) is installed in the
expansion pipe upstream of the diaphragm
expansion tank (1) according to
DIN EN 12828.
 Mount the connection screw (2) tightly to the
connection piece of the diaphragm
expansion tank and fasten it to the tamper-
proof valve using the enclosed gasket.
 After installation, the fully open valve (turned
counter-clockwise all the way to the stop)
must be secured against inadvertent closing
by means of wire and a lead seal.
 Procedure for maintenance work at the
expansion tank:
Open the seal and remove the cap (5).
-
Close the "tamper-proof valve" using an
-
Allan key size 6, clockwise all the way to
the stop.
Description
 Tamper-proof valve made of brass,
 With boiler feed and drain cock
 With cap, wire and lead seal
 With screw connection for diaphragm
0 - 120 °C
max. 10 bar
kvs: 1,5 m³/h
Open the boiler feed and drain cock
-
(4) at the side and drain the diaphragm
expansion tank.
Perform the required maintenance
-
work at the diaphragm expansion tank
(1).
Close the boiler feed and drain cock
-
when you are done with the
maintenance work.
Open the tamper-proof valve (3) (turn
-
counter-clockwise all the way to the
stop) and secure it with the cap and a
lead seal (5).
connection
G1" with shut-off valve, adjustable with a
size 6 Allan key
expansion tank G1".
1 Diaphragm expansion tank
2 Screw connection
3 Tamper-proof valve
4 Boiler feed and drain cock
5 Cap with lead seal and wire