Section 2.0 – Machine Setup
2.0 Setup Instructions
The CLSR-ST is fully tested prior to breakdown and delivery to the customer. As a
result, this manual provides a section on machine setup so that you can install the
machine. Please read this manual in its' entirety and follow all ABM instructions,
especially the inspections. Total setup time, less power and air hook-up, should take
approximately 1 hour.
Upon receipt of the machine, check to ensure that there is no visible damage Note: Some
components may be in different locations depending on the version of the machine.
2.1 Machinery Positioning
Determine the location in your facility for the panel cutter. Attach the four (8) machine
legs supplied with the machine to the plates that were used to bolt the machine to its skid.
Level and position the machine in the desired location. Though not required, ABM
recommends that the machine be bolted to the floor.
2.2 Power Installation
This section will confirm that the electronics of the machine is functioning properly.
WARNING
: ELECTRICAL SHOCK HAZARD. IF A PROBLEM IS FOUND,
YOU SHOULD NOT ATTEMPT TO REPAIR IT WITH THE POWER ON.
DISCONNECT THE MACHINE PRIOR TO ADJUSTING ANY COMPONENTS
WITHIN THE ELECTRICAL CABINET.
Run a 220VAC, single phase, 10A line to the main cabinet location. As with any
machine, power should be run through approved conduit and ducting with proper
termination. ABM does not supply a main power disconnect with the machine and
recommends that the customer install one. You may connect the power to the machine at
this time.
Turn the main power switch to ON. An LED on the switch box will signify that power
has been applied. Wait a few moments for the system BEEP. After the BEEP has
sounded, the machine may be operated according to the procedures outlayed in the
PFAFF manuals found in the appendix.