PRESTART PROCEDURES:
1. Position the valves on the Biological Recycling System as follows for start up of the system.
A. Aeration Pump Inlet Valve: Turn valve open.
B. Aeration Pump Outlet Valve: Turn valve open.
C. Water Outlet Valves: Turn valves closed.
2. Be certain all plumbing/hoses are tight and properly connected.
3. Be certain the incoming air to the Air Injectors is not obstructed.
4. Be certain all switches on the Control Panel are in the "OFF" position.
START-UP:
1. Ensure all Hold Down Angles are fastened into Biological Tank.
2. Turn power from main disconnect "ON".
3. Turn on the Master Switch, water from the Freshwater Inlet will start filling the Product Tank.
4. When the Product Tank is full, prime the Transfer Pump by opening the union immediately after the Transfer Pump
until water starts to flow out, then tighten union again.
5. Turn on the Transfer Pump Switch to pressurize the Manifold and Pressure Tank.
6. Turn on the Sump Pump Switch.
OZONE OPTION ONLY:
a. Prime the Ozone Pump by opening the union immediately after the Ozone Pump until the water starts to
flow out, than tighten the union again.
b. Turn on the Ozone Pump Switch.
7. Operate the aeration loop on the Biological System for one hour before adding Mi-T-M microbes.
Operator's Manual
PREPARATION
15