eClick installation instructions
Scenario D: double power supply line to the eClick with eSmartMeter
(separate Power supply line for self-supply)
1. Drill a hole for the AUX cable in the corresponding
routing plate, and insert the provided M20 cable gland.
2. Replace the routing plate in the eClick, and press
this on firmly to ensure tightness.
3. Tighten the cable gland to ensure tightness.
Caution
1. Detach the cable routing plate from the top (T) or the bottom (B).
2. Introduce the cable through the routing plate, and cut to length.
3. Replace the cable routing plate.
4. The pre-wired cables from the eSmartMeter must be placed
on the mains board.
5. Before you can route the AUX lines, you must first remove the
blue and black jumper on the mains board.
6. Now place the wires on the contacts as depicted in the figure, and
tighten the screws on the terminals with a torque of 1,2 - 1,5 Nm.
U
3a
3b
All manuals and user guides at all-guides.com
Caution
If single-phase connection
is required, the mainboard or
eSmartMeters must not be
connected to L2 or L3! The
supply line L1 must always
be connected to L1 of the
mainboard or eSmartMeter.
3b
3a
For communications with the eSmartMeter,
connect its 3a output to the 3b input (cable provided).
The separate AUX supply line must be protected
with its own RCD rated at 6 A.
M20 cable gland
Note
The cable cross-section of the
separate AUX supply line may
not exceed 1.5 mm².