Descargar Imprimir esta página

Start-Up And Shutdown - Salicru EQUINOX EQX2 4002-T Manual De Usuario

Ocultar thumbs Ver también para EQUINOX EQX2 4002-T:

Publicidad

Idiomas disponibles

Idiomas disponibles

6. START-UP AND SHUTDOWN.

Electric arc hazard. Do not open any DC isolating switch if
the unit is under load.
Follow the steps indicated below to start the inverter:
1.
Activate the inverter switch/isolating switch and set it to ON.
2.
Make sure that the solar field is connected. Activate the circuit
breakers to enable the photovoltaic power supply.
3.
Ensure the presence of grid voltage. Activate the circuit
breakers to enable the grid supply. Without a grid, the unit will
not activate the generation mode.
OFF
OFF
4.
The unit will start. The LCD screen will turn on. The next section
describes the steps that must be followed and the operation
of the console.
Follow the steps below to stop and turn off the inverter:
1.
Disable the grid power supply. Without a grid, the unit will stop
generating.
2.
Turn off the solar field supply. Activate the circuit breakers to cut
off the photovoltaic power supply.
3.
Deactivate the inverter's switch/isolating switch and set it in the
OFF position.
70
ON
ON
OFF
4.
The unit will stop. When the internal capacitors of the DC bus
are fully discharged and have no voltage, the LCD screen will
turn off.
ON
ON
SALICRU

Publicidad

loading

Este manual también es adecuado para:

Equinox eqx2 5002-tEquinox eqx2 6002-tEquinox eqx2 8002-tEquinox eqx2 10002-tEquinox eqx2 12002-tEquinox eqx2 15002-t ... Mostrar todo