1. Strip the incoming AC supply cable as shown below, and crimp the copper wire to the appropriate
OT terminal (according to DIN 46228-4, to be provided by the customer).
Single phase
Three phase
2. Install the incoming AC supply cable.
Option 1
Remove the cable gland from the bottom of the
enclosure.
1
ENGLISH
Object
Description
A
External diameter
B
Copper conductor cross-section
C
Stripping length of the insulated conductors
D
Stripping length of the cable outer sheath
Note: The PE conductor is at least 5mm longer than the L and N conductors.
Object
Description
A
External diameter
B
Copper conductor cross-section
C
Stripping length of the insulated conductors
D
Stripping length of the cable outer sheath
Note: The PE conductor is at least 5mm longer than the L and N conductors.
Thread the incoming AC supply cable through the
cable gland, loosen the nut (A).
2
Install the cable gland on the bottom of the
enclosure, fasten the nut (B). And then fasten the
nut (A).
3
Value
18-21mm
4-16mm
2
12mm
75mm
Value
18-21mm
4-16mm
2
12mm
75mm
A
5