When the piping length from the outdoor unit to the farthest HBC controller is
longer than 30.5 m (100 ft)
Amount of
High-pressure pipe
additional
ø22.2 total length
=
charge (kg)
× 0.21 (kg/m)
Amount (kg/HBC
+
controller)
3.0
* Amount of refrigerant to be charged for
single-module units
* In the case all connected indoor unit
models are Case 1, add the following
amount of refrigerant.
Case 1: PEFY-WL06/24NMAU-A**
→ Add 0.55 kg per PEFY-WL06/24NMAU-A**.
(2) Units "ft" and "oz"
<Formula>
When the piping length from the outdoor unit to the farthest HBC controller is
30.5 m (100 ft) or shorter
Amount of
High-pressure pipe
additional
ø7/8 total length
=
charge (oz)
× 2.48 (oz/ft)
Outdoor unit model
PURY-(E)P72T/
YNU
PURY-(E)P96T/
YNU
+
PURY-(E)P120T/
YNU
PURY-(E)P144T/
YNU
PURY-(E)P168T/
YNU
Table <B>
* Amount of refrigerant to be charged for
single-module units
* In the case all connected indoor unit
models are Case 1, do Not add the
refrigerant listed in table <B>.
Instead, add the following amount of
refrigerant.
Case 1: PEFY-WL06/24NMAU-A**
→ Add 20 oz per PEFY-WL06/24NMAU-A**.
When the piping length from the outdoor unit to the farthest HBC controller is
longer than 30.5 m (100 ft)
Amount of
High-pressure pipe
additional
ø7/8 total length
=
charge (oz)
× 2.27 (oz/ft)
Amount (oz/HBC
controller)
+
106
* Amount of refrigerant to be charged for
single-module units
* In the case all connected indoor unit
models are Case 1, add the following
amount of refrigerant.
Case 1: PEFY-WL06/24NMAU-A**
→ Add 20 oz per PEFY-WL06/24NMAU-A**.
4.5. Drain piping work
1. Drain piping work
Tilt the drain pan so that the water will flow toward the drain socket.
8
High-pressure pipe
High-pressure pipe
ø19.05 total length
ø15.88 total length
+
+
× 0.14 (kg/m)
× 0.10 (kg/m)
High-pressure pipe
High-pressure pipe
ø3/4 total length
ø5/8 total length
+
+
× 1.73 (oz/ft)
× 1.19 (oz/ft)
Amount (oz/HBC
Amount (oz)
controller)
+
53
106
53
106
89
142
High-pressure pipe
High-pressure pipe
ø3/4 total length
ø5/8 total length
+
+
× 1.52 (oz/ft)
× 1.09 (oz/ft)
[Fig. 4.5.1]
①③
① Unscrew the two screws that are holding the side panel on the right side of the control
box.
② Tilt the drain pan.
③ Screw down the screws with the drain pan tilted.
Ensure that the drain piping is downward (sloped gradient of more than 1/100) to
the outdoor (discharge) side. If it is impossible to take any downward pitch, use
an optionally available drain-up mechanism to obtain a downward pitch of more
than 1/100.
Ensure that any cross-wise drain piping is less than 20 m [65 ft]. If the drain
piping is long, support it with metal brackets to prevent it from bending, warping,
or vibrating.
Use a hard vinyl chloride pipe for drain piping.
Ensure that collected pipes are 10 cm [3-15/16 in] lower than the unit body's
drain port.
Do not provide any odor trap at the drain discharge port.
Put the end of the drain piping in a position where no odor is generated.
Do not put the end of the drain piping in any drain where ionic gases are
generated.
When connecting the drain pipe to only one drain socket, use the drain
socket at the bottom, and cover the top one.
[Fig. 4.5.2]
Max. 20 m [65 ft]
1.5-2 m [5-6 ft]
Correct piping
×
Wrong piping
A Insulation (9 mm [6/16 in] or more)
B Downward slope (1/100 or more)
C Support metal
K Air bleeder
L Raised
M Odor trap
Grouped piping
D PVC TUBE
E Make it as large as possible. About 10 cm [3-15/16 in].
F Indoor unit
G Make the piping size large for grouped piping.
H Downward slope (1/100 or more)
I O.D. ø38 mm [1-8/16 in] PVC TUBE for grouped piping. (9 mm [6/16 in] or more
insulation)
J HBC controller
1. Insert the adapter (not supplied) into the drain port.
• Apply wraps overlapping of sealing tape (2 times)
• Torque the drain pan adapter to 2.5 Nm+/–0.5 [22 in-lb]
2. Attach the drain pipe (PVC TUBE, not supplied).
(Attach the pipe with glue.)
3. Perform insulation work on the drain pipe (PVC TUBE) and on the socket (includ-
ing elbow).
4. Check the drainage.
①③