3.2
Option 2: Installation to the wall with wall brackets
DN 25: 128 mm
DN 32: 156 mm
45 mm
105 mm
1. Determine the position for installation.
2. For two-, three- and fourfold distribution manifolds you need one set of wall brackets.
For five- and sixfold distribution manifolds, two sets of wall brackets are needed.
Copy the mounting holes onto the mounting surface.
3. Drill the holes and insert appropriate wall plugs.
4. Fix the wall brackets to the wall using the screws and washers.
5. Mount the acoustic decoupling
6. Take off the insulating front shell of the distribution manifold.
7. Put the distribution manifold with the insulating back shell onto the wall brackets.
8. Screw the distribution manifold onto the wall brackets with the enclosed washers
and nuts.
18
375 mm
993x1x3-mub-ml – V01
3 Assembly and installation [specialist]
2017/01