Fireplace Concrete Pad Construction:
Call 811 for information on underground utility marking. Select desired location and excavate 52" L x
65 3/4" W x 12 3/4" D area for concrete pad. Fill excavated area with approximately 6" of ¾" clean
gravel, compacting every 3". Frame remaining 4" with 2" x 4" lumber to create a level pad. (Be sure 2"
x 4" wood frame is perfectly level, front to back and side to side) See attached drawing for details of
steel reinforcement rod placement. Fill 2" x 4" wood frame with a 4,000 PSI strong concrete mix.
*Allow pad to cure for minimum of 48 hours.
*Note: (Wood Box Additions) If you are going to add fire wood box extensions, either a single unit or a
set it will be necessary to construct an additional concrete pad for each unit added.
Chimenea Construcción Base de Concreto:
Llame al 811 para obtener información sobre la utilidad de metro marcado. Seleccione la ubicación de-
seada y excavar 52" de largo x 65 3/4" W x 12 3/4" D área de plataforma de concreto. Llene la zona ex-
cavada con aproximadamente 6 "de ¾" limpia grava, compactando cada 3". Marco restantes 4"con 2" x
4" de madera para crear una plataforma de nivel. (Asegúrese de 2" x 4" marco de madera está perfecta-
mente horizontal, de adelante hacia atrás y de lado a lado) Véanse los detalles del dibujo para la coloca-
ción de varillas de acero de refuerzo. Llene 2" x 4" marco de madera con una mezcla de concreto 4000
PSI fuerte.
*Deje que la almohadilla para curar por un mínimo de 48 horas.
* Nota: (El texto añadido Caja para la lena) Si usted va a agregar el fuego extensiones caja para la lena,
ya sea una sola unidad o conjunto será necesario construir más plataformas de concreto para cada uni-
dad adicional.