3.
Commissioning
On commissioning you have to adjust primarily the language and
the system scheme!
Arr 1
Arr 3
Arr 5
Arr 7
Arr 9
14
1. AC power supply must be activated. The
controller passes an initialisation phase. After
having fi nished the initialisation, the controller
is in automatic operation with factory settings.
The preadjusted system scheme is Arr 1.
1
forward
2. - select Arr
SET
3
(selection / ad-
justment mode)
2
backwards
Now the controller is ready for operation and
should enable an optimum operation of the solar
system by the factory settings made.
Arr 2
System survey:
Arr 1 : standard solar system
Arr 2 : solar system with heat exchange
Arr 3 : solar system with after-heating
Arr 4 : solar system with store charge in layers
Arr 4
Arr 5 : 2-store solar system with valve logic
Arr 6 : 2-store solar system with pump logic
Arr 7 : solar system with 2 collectors and 1
Arr 8 : solar system with after-heating by solid
Arr 6
Arr 9 : solar system with heating circuit re-
Arr 10: solar system with 1 tank and 1 swim-
Arr 8
Arr 10
- change into SET-mode
- select the system scheme by Arr-characte-
ristics
- adjustment is saved by pressing button SET
store
fuel boiler
verse raising
ming pool
Commissioning