Installation - ProMinent DULCOTEST OZE 3-mA-2 ppm Instrucciones De Servicio

Ocultar thumbs Ver también para DULCOTEST OZE 3-mA-2 ppm:
Tabla de contenido

Publicidad

Idiomas disponibles

Idiomas disponibles

6
IMPORTANT
• Do not switch off the measuring system during interval operation!
• In case of sensor failure, an incorrect measuring value may be
mA variant for
connection to
third party
devices
IMPORTANT
• The sensor is not galvanically isolated from the sample water. Ensure
• Do not exceed the power supply of 16 Vdc, even not for a short time!
• Please note when connecting to third party devices:
when
connecting
to ProMinent
®
devices
When connecting to ProMinent control units (e.g. DULCOMETER
safety requirements on the interface are automatically met.
The OZE 3-mA is a sensor with a passive 4-20 mA two-wire interface, i.e. the
power is supplied externally, e.g. via the control unit.
Electrical installation
ProMinent
®

Installation

If required, switch on metering unit time-delayed!
present at the input of the control unit. Design the electrical
installation such that it will not result in any uncontrolled metering
and consequential damages!
that the sensor is electrically isolated from all other consumers!
The connected control unit must be electrically isolated both from
the sensor and the power supply!
The power source must be able to provide at least 16 Vdc at a min. of
35 mA! An insufficient power supply results in an incorrect reading!
Voltage supply:
max. load:
Turn the adapter of the sensor one quarter turn anti-clockwise and pull off
(bayonet mount).
Loosen the clamping screw of the M12 screw fitting and feed through the
measuring line from the control unit.
Strip the cable ends and connect to the 2-wire connector:
1 = Plus, 2 = Minus.
16-24 Vdc, min. 35 mA at 16 Vdc
1 W
Installation
®
D1C), the
31