Initial Operation - TBH LN-Serie Instalación Y Manual De Funcionamiento Y Mantenimiento

Ocultar thumbs Ver también para LN-Serie:
Tabla de contenido

Publicidad

Idiomas disponibles
  • MX

Idiomas disponibles

6
Compressed air tank
7
Filter housing with saturation filter / filter cartridge
8
Dust container
9
Castors / machine base / tilt lock, depending on the type of device
4.4

Initial Operation

• First, follow the steps according to chapter 4.3
• Check if the system stands stable and check pipe connections
• Check correct power connection. The 400V connection must provide a neutral conductor (as the system works with
230V control voltage). Observe rotating field.
• Switch on system by the main switch
• The LEDs at the front label will be blinking for 2 sec and thereby indicate the system's self check
• The system will start itself after the self-check
• Turbine / ventilator speed can be set at the turning knob
• In case of trouble, see chap. 5 and 7
4 Installation, Initial Operation
53-198

Hide quick links:

Publicidad

Tabla de contenido
loading

Productos relacionados para TBH LN-Serie

Tabla de contenido