INSTALLATION
START PUMP
1. Take the pump out of standby. First, press and continue to hold
. Prime the pump. First, press and continue to hold
STBY
Once the pump is primed, release both buttons. Observe flow as actuated by the
system and check all connections for leaks.
2. After suitable amount of dosing time, perform tests for desired readings (e.g., pH or
ppm). If necessary, fine tune dosing levels by adjusting the percentage or by
adjusting the solution strength.
NOTE: If the signal indicator flashes during the run cycle in the 1, 5, 10, 20, or 60 seconds
modes, the meter contacting rate is too high for the setting programmed. Revisit the dry
contact water meter programming section and correct the setting to avoid incorrect dosing.
NOTICE: The injection point and fitting require periodic maintenance to clean
any deposits or buildup. To allow quick access to the point of injection, Stenner
recommends the installation of shut-off valves.
NOTICE: Be sure to replace cover and self-tapping screw.
continued
USA and Canada 800.683.2378, International 904.641.1666
, then press
MODE
, then press
MODE
PRIME
Econ FP
.
27