OPERATION
Nose Assembly Operation
Refer to the illustration below.
1. Pull out the ring pull detent pin (1).
2. Rotate the nose assembly to the correct position for
the pull.
3. Make sure the ring pull detent pin (1) is engaged
with the circle tube.
Boom Operation
Refer to the illustration below.
Raising the Boom
Make sure to raise the top extension first before raising
the mid extension.
Note: When raising either extension, stop
when the paint color changes from green
to silver. Do not raise the extensions past
the fourth hole from the end as shown
here.
1. Pull out the ring pull detent pin (2).
2. Extend the top extension to the correct height.
3. Pull out the ring pull detent pin (3).
4. Extend the mid extension to the correct height.
5. Make sure the ring pull detent pins (2, 3) are
engaged with the boom tubes.
Lowering the Boom
1. Hold the boom tube with one hand. Be aware of the
weight.
2. Lift up the boom tube slightly and pull out the ring
pull detent pin.
3. Move the boom tube to the correct height while
pulling the ring pull detent pin. DO NOT allow the
boom tube to drop freely.
4. When the correct height is reached, make sure the
ring pull detent pin is engaged with the boom tube.
Handle Operation
Refer to the illustration below.
Rotating the Handles
1. Pull out the ring pull detent pins (4).
2. Rotate the handles to the next position.
3. Make sure the pins are engaged to the handle.
Greenlee / A Textron Company
Setting the Handle Height
Changing the boom tube height also changes the
handle height. Refer to "Boom Operation" above for
more information.
Green
Ring Pull Detent Pin (4)
Silver
Ring Pull Detent Pin (1)
Handle
Ring Pull Detent Pin (3)
12
4455 Boeing Dr. • Rockford, IL 61109-2988 USA • 815-397-7070
®
G3 Tugger
System
Nose Assembly
Ring Pull Detent Pin (4)
Top Extension Boom Tube
Mid Extension Boom Tube
Ring Pull Detent Pin (2)