01. Dig a generously sized foundation pit to house the foundation
box (fig. 3): prepare a drain pipeline for draining off water and avoid
the build-up of water.
02. If the gate is equipped with its own mechanical stops (fig. 2) skip
directly to point 3. Otherwise secure the opening limiter accessory to
the box (see paragraph 4).
03. Place the box inside the foundation hole; the stud must be
aligned with the axis of the hinge (fig. 3).
04. Provide a duct for the electrical cables and a drainage pipe.
05. Bury the foundation box in concrete, making sure it is set level.
06. Mount the control bracket on the box's stud along with the ball
(fig. 4).
07. Set the gate leaf on the release lever and weld them securely.
08. Grease using a suitable grease nozzle.
3
1- Hinge
2- Pin
4
3
4
5
1
Release lever
2
Connecting lever
3
Ball
3- Concrete
1
2
4
Control bracket
5
Pin
3.6 -
Installation of INTRO Gearmotor
01. Remove the nuts and washers shown in the figure on the right
(fig. 5).
02. Place the gearmotor inside the foundation box making sure it
faces the correct direction.
03. Secure the gearmotor with the previously removed washers and
nuts.
04. Connect the gearmotor to the gate by means of the connecting
lever (2) (fig. 4).